Gantt chart: subtasks and dependent tasks do not behave as expected

Post Reply
rh@syconics.de
Sponsor
Sponsor
Posts: 92
Joined: 08 Feb 2016, 18:03
Name: Reinhard Hansmann
Location: Frankenberg/Eder (Germany)
Company Name: syconics UGhb & Co. KG

Gantt chart: subtasks and dependent tasks do not behave as expected

Post by rh@syconics.de »

Dear Sergey,

the new Gantt chart seems not behaving as expected to me for the following reasons:

1.) If a parent task is moved (start-date forward or backward) the subtasks don't move automatically accordingly. This results in subtasks exceeding the boundaries of the parent task. subtasks should never exceed the boundaries of a parent task.

2.) If tasks have dependencies to another task and this task is moved (start-date changes), all depending tasks should move accordingly. Why else should I specify dependencies in project management if dependencies aren't resolved changing timelines? This is standard behavior in all other project management tools I know.

As far as I know, the new Gantt supports all these requirements. What do You think about making use of the new possibilities? I think in this case it makes sense to implement "duration" and "offset" fields to projects and tasks tables.

Best regards
Reinhard
User avatar
support
Site Admin
Posts: 6215
Joined: 19 Oct 2014, 18:22
Name: Sergey Kharchishin
Location: Russia, Evpatoriya

Re: Gantt chart: subtasks and dependent tasks do not behave as expected

Post by support »

well, all these features are paid https://dhtmlx.com/docs/products/dhtmlx ... ures.shtml
I can't include product with commercial license in opensource product.