Gantt Chart not organised

Posted: 20 Sep 2022, 05:13
by vesb
Hi All,
I use a gantt chart for sub-entity tasks. in the report,
the gantt chart is not organized. how to rearrange order in gantt chart.

thanks in advance

RY

Re: Gantt Chart not organised

Posted: 20 Sep 2022, 08:22
by support
Records sorted by Start date in Gantt

Re: Gantt Chart not organised

Posted: 13 Nov 2022, 18:50
by vesb
Hi Sergey,

The record seems like not sorted with the start date.

What might be wrong in my setting?

Thanks in Advance

br

Razli Yahya

Re: Gantt Chart not organised

Posted: 17 Nov 2022, 08:51
by support
probably do you use Tree listing type and if you sort task in this case, then tasks will be sorted by sort order in gantt too.