Hi there!
I just updated from 2.8 to 2.9.2 and I am experiencing some problems with Pivot Calendar Reports.
I have a couple of types of entities that I add directly to the calendar on my dashboard.
Out of 5 different types of entities, 2 of them do not work and I have no idea why.
I have full rights as administrator and I made sure in the reports there are full rights to edit and create.
I will give one example of the behavior: I click the date and I get a modal window with 3 types of entities I can add to this date. I select "tasks" and then the second modal opens with a question to which project do I want to add the task. I select the project and then the modal disappears and the screen freezes.
I don't experience the same behavior if there is no parent entity to select.
If there is no parent entity all works fine.
I hope we can fix that. I really loved to use pivot calendars.
Thanks for your hard work and have a great day!
Best,
Maria
Pivot Calendar in 2.9.2
-
- Posts: 9
- Joined: 04 Mar 2017, 21:05
- Name: Maria
- Location: Sofia, Bulgaria
- Company Name: More By Us
- Contact:
-
- Posts: 9
- Joined: 04 Mar 2017, 21:05
- Name: Maria
- Location: Sofia, Bulgaria
- Company Name: More By Us
- Contact:
Re: Pivot Calendar in 2.9.2
I changed the PHP version and experimented with all between 7.2 and 8, it didn't make any difference.
BUT for some reason, I was able to add one child entity to the parent entity from the pivot calendar with zero changes to the settings.
A second later it didn't work again. Maybe it is some server setting I need to change?
BUT for some reason, I was able to add one child entity to the parent entity from the pivot calendar with zero changes to the settings.
A second later it didn't work again. Maybe it is some server setting I need to change?
- support
- Site Admin
- Posts: 6215
- Joined: 19 Oct 2014, 18:22
- Name: Sergey Kharchishin
- Location: Russia, Evpatoriya
Re: Pivot Calendar in 2.9.2
To fix something I have to have way how to reproduce it.
Try to reproduce this issue on personal demo with test database and I will look at it https://www.rukovoditel.net/demo.php
Try to reproduce this issue on personal demo with test database and I will look at it https://www.rukovoditel.net/demo.php
-
- Posts: 9
- Joined: 04 Mar 2017, 21:05
- Name: Maria
- Location: Sofia, Bulgaria
- Company Name: More By Us
- Contact:
Re: Pivot Calendar in 2.9.2
Thank you very much!
I managed to recreate the problem in the demo environment.
Please try to add a task in the Test Calendar on the left (dashboard).
My demo is created by morebymaria@gmail.com
Best,
Maria
I managed to recreate the problem in the demo environment.
Please try to add a task in the Test Calendar on the left (dashboard).
My demo is created by morebymaria@gmail.com
Best,
Maria
- support
- Site Admin
- Posts: 6215
- Joined: 19 Oct 2014, 18:22
- Name: Sergey Kharchishin
- Location: Russia, Evpatoriya
Re: Pivot Calendar in 2.9.2
I see. Try to do this fix viewtopic.php?p=12245#p12245
Let me know if it helps.
Let me know if it helps.
-
- Posts: 9
- Joined: 04 Mar 2017, 21:05
- Name: Maria
- Location: Sofia, Bulgaria
- Company Name: More By Us
- Contact:
Re: Pivot Calendar in 2.9.2
It works, yey! Thank you very much!