Page 1 of 1

Gantt Chart mix with other project

Posted: 27 Jul 2016, 07:10
by khendy
hi Support,

I am using ver 1.7.1 and ext 1.3.1 I have 2 cases :

1. while we open a project and click on the gantt chart directly it is fine we can see that project gantt chart but after we click to project info and then back to gantt chart we can see all projects gantt chart that all we have in one project all mix there, but if we go back to project on the menu and then direct to gantt chart the chart is fine

2. we cannot change the duration on gantt chart , after we save it back to 1 day

please advice

thank you

Re: Gantt Chart mix with other project

Posted: 27 Jul 2016, 07:30
by support
can you provide screenshots, please?

Re: Gantt Chart mix with other project

Posted: 27 Jul 2016, 07:44
by khendy
hi Support,

here is the screenshot on the attachment for case 1

Re: Gantt Chart mix with other project

Posted: 27 Jul 2016, 07:44
by khendy
here for case 2

Re: Gantt Chart mix with other project

Posted: 27 Jul 2016, 08:44
by support
Thank you, found this issue (issue in generating url path to gantt chart)